out of all the mods folks have done, aint none of yaw got any insight to share? only reason for even thinking bout adding a jib is. our chilean bird is coming home by ship and the port cranes are expensive by the hr, and if we are down for any short amount of time, the crane will go to another job on the docks and no tellings when we would get it back. iv called several rental companies and no joy. haven't had time to call a crane and rigging place to see if they rent out their boom/crane trucks.
all we should have to do it put 6 blades on, but things happen and something could have gotten damaged during shipping or as with head seals, they could decide to leak and reseal after a ground run. either way, we are 19.6' to the top of the aft rotor and i need another 5-6' for blade cradle and a lil cable up room.
this extension is a last ditch attempt to make mission happen, but i'll only have about a wk to get it built, yank part my rear hubs, repack the bearings and get down to beaumont.